On the second floor, the window and door carpentry trim-out is complete, the bathrooms are being tiled and the painting of the walls and ceilings is ongoing. Installation of the millwork on the first and second-floor units is nearing completion. On the third floor, all units have been tiled and painting of the walls and ceilings and tiling of the balconies is ongoing. Exterior finish works are also ongoing.
|