Loop 1604 from SH 16 to I-35
TxDOT is moving forward with plans to improve approximately 23-miles of Loop 1604 from SH-16 (Bandera Road) to I-35 in north Bexar County. The Loop 1604 Expansion Project involves several transportation improvements that are designed to improve mobility, reduce congestion and enhance safety along the high-traveled corridor.
Improvements
The project includes the following improvements:
- Expanding Loop 1604 from a four-lane expressway to ten-lane expressway with the addition of two general purpose lanes in each direction.
- Adding one high-occupancy vehicle lane in each direction.
- Reconfiguring the layout of auxiliary lanes and entrance and exit ramps.
- Removing the cloverleaf connectors.Replacing the cloverleaf interchange at IH 10/LP 1604 with a five-level direct connect interchange
- Adding direct connectors.
- Replacing the signalized frontage road intersections with a continuous flow configuration.Upgrading Blanco Road and LP 1604 to an innovative intersection
- Accommodations for bicyclists and pedestrians, water quality protection, and other highway features.
- All improvements are located within the existing right of way and easements.
Project segments
Segment 1: Loop 1604 from SH 16 (Bandera Road) to I-10
- Download segment 1 map
- Estimated Start: Summer 2021
- Estimated Completion: 2025
- Estimated Cost: $148 million
Segment 2: Loop 1604 and I-10 Interchange
- Download segment 2 map
- Estimated Start: 2022
- Estimated Completion: 2027
- Estimated Cost: $418 million
Segment 3: Loop 1604 from I-10 to US 281
- Download segment 3 map
- Estimated Start: Fall 2021
- Estimated Completion: 2025
- Estimated Cost: $244 million
Segment 4: Loop 1604 from US 281 to Redland
- Download segment 4 map
- Estimated Start: 2024
- Estimated Completion: 2027
- Estimated Cost: $178 million
Segment 5: Loop 1604 from Redland to Judson Rd.
- Anticipated Letting Date: 2024
- Estimated Start: Late 2024
- Estimated Completion: 2027
- Estimated Cost: $205 million
Segment 6: Loop 1604 from Judson Rd. to I-35
- Anticipated Letting Date: 2025
- Estimated Start: Late 2025
- Estimated Completion: 2028
- Estimated Cost: $203 million
Benefits
Once complete, the planned project improvements will reduce congestion, improve mobility and enhance safety by:
- Decreasing future travel times by as much as 80 minutes
- Increasing capacity with non-toll general purpose and HOV lanes
- Integrating multimodal improvements with the construction of continuous sidewalks and bicycle accommodations
- Creating a fully directional, five-level interchange at I-10 and Loop 1604
Project updates
TxDOT is committed to providing timely project updates as they are available. If you are interested in receiving updates, please subscribe.
Construction impacts to traffic
Throughout construction of these improvements, drivers will experience temporary traffic shifts and overnight lane closures on the mainlanes and frontage roads, as well as temporary daytime and overnight ramp closures.
Daytime work is anticipated to take place Mondays through Saturdays, while nighttime work and any necessary lane closures are anticipated to take place between 9 p.m. and 5 a.m., Sunday evenings through Friday mornings.
Traffic updates
Permanent and temporary digital message boards placed along the route will alert drivers in real-time to lane closures, traffic congestion and construction activity.
For the latest on construction closures and traffic shifts, follow us on Facebook and Twitter or visit the San Antonio District’s Go Ahead! Blog.
Public involvement
The purpose of the open house is to share project information and updates, present proposed schematics of the proposed project and collect input from the community. TxDOT is committed to working closely with the community on this project. All input will be considered as TxDOT moves forward in developing a plan that will enhance the safety of this corridor while preparing for future growth.
- Sept 24, 2019 - Open House
- Sept 25, 2019 - Open House
- Documentation of Public Meetings - Sept. 24 -25, 2019
- Sept. 10, 2020 - Virtual Public Hearing
- Documentation of Public Hearing - Sept. 10, 2020
- Notice Finding of No Significant Impact and Final Environmental Assessment
Downloads
Schematics
- Loop 1604 from SH 16 (Bandera Rd) to Kyle Seale Parkway
- Loop 1604 from Kyle Seale Parkway to I-10
- Loop 1604 from I-10 to Bitters Road
- Loop 1604 from Bitters Road to Stone Oak Parkway
- Loop 1604 from Stone Oak Parkway to Redland Road
- Loop 1604 from Redland Road to O’Connor Road
- Loop 1604 from O’Connor Road to UPRR
- Loop 1604 from UPRR to I-35
- I-10 from Camp Bullis Road to LP 1604
- I-10 from LP 1604 to De Zavala Road