Paving, sidewalk and drainage improvements on NY State Route 7 in the Village of Otego, Otsego County
A public information meeting was held on September 22, 2021. A copy of the presentation slides is available at the Community Outreach Tab.
Project Overview
Project Status
The project has been Completed 10 days ahead of schedule.
The Bid Opening was on 03/10/2022.
Project Schedule
Award of Contract
Original Contract Completion Date*
Substantially Completed
Construction Schedule Variance from Contract Award**
Award of Contract
Original Contract Completion Date*
Substantially Completed
Construction Schedule Variance from Contract Award**
05/10/2022
12/31/2023
12/08/2023
On-Time (Green)
** Schedule Variance Key:
Red - Current Schedule Variance is > 10% of Original Completion
Yellow - Current Schedule Variance is > 5% and <=10% of Original Completion
Green - Current Schedule Variance is within 5% of Original Completion
Construction Costs
Contract Award Cost
Approved Cost Changes
Current Construction Contract Cost
Cost Variance of Construction Contract*
Contract Award Cost
Approved Cost Changes
Current Construction Contract Cost
Cost Variance of Construction Contract**
$5,296,706
$818,957
$6,115,662
Red
**Cost Variance Key:
Red - Current Construction Costs are > 10% of Contract Award Cost
Yellow - Current Construction Costs > 5% and <=10% of Contract Award Cost
Green - Current Construction Costs are within 5% of Contract Award Cost
*Project Schedule Defintions:
Original Contract Completion Date - This is a contractual date, at the time the Contractor is Awarded the contract,representing when the Contractor is obligated to complete all of the work required in the contract and will no longer have a presence within the highway Right-of-Way.
Estimated Substantial Completion Date - This is the day the public (including vehicles and pedestrians) has full and unrestricted use and benefit of the facilities both from the operational and safety standpoint.
This project receives funding from the following sources: Federal: Yes
State : Yes
Local : Yes
The scheduled dates shown are approximations only. For more detailed information, please utilize the "Contact Us" information provided.
Statewide Transportation Improvement Program (STIP)
The Statewide Transportation Improvement Program (STIP) is a list of every project
in New York State for which Federal funding is proposed to be used and that is
scheduled to begin during the designated three Federal fiscal year time frame.
To review the STIP Project List by Region please see the
STIP Project Report.